- Possibility of connecting to three (3) existing circuits. Two circuits are connected to the sub station "Tipitapa" and one of them to the "Oriental" sub station in a radius of 4 km.
- 13.8 kVa with capacity 12Mva electrical line and delivery voltage - 7.6/13.2 KVa and the conductor caliber of the derivation of 3/0, where 185 Kva are connected
- Line installation of 138 Kv project is being developed, it will be connected to the national electrical system, and also a construction of independent substation of 15 Mva is in process. All these, in areas next to the park which will allow direct purchase for the generators with competitive tariffs.